Carmichael mine: environmental impact will be unknown for years
Government backdown means Indian owners won’t be required to replace razed critically endangered habitat until two years into the project
Construction of Australia’s largest ever mine will be well underway before its impact upon the environment is known, with a requirement to replace critically endangered habitat razed by the project pushed back by two full years after a backdown by the federal government.
Documents seen by Guardian Australia show that the government scaled back its initial environmental conditions for the Carmichael mine in central Queensland following a request by Adani, the proponent.
The changes effectively mean the $16.5bn mine’s impact on crucial groundwater supplies, beyond the 297bn litres it will extract from aquifers, will be largely unknown until the project is at an advanced stage.
More than 35,000ha of habitat, containing the endangered black-throated finch and the vulnerable yakka skink, will be flattened for the mine. Indian firm Adani was initially required to secure land elsewhere to compensate for this loss prior to construction, but will now not have to do this until two years after the project starts.
The Carmichael mine is being enthusiastically backed by the Queensland government, which has offered to fund part of the project. The mine, which was approved in July, will extract 60m tonnes of coal a year for export to India. Emissions from the burned coal will create an estimated 128m tonnes of carbon dioxide a year, around four times the annual greenhouse gas output of New Zealand.
In draft conditions drawn up by the federal Department of the Environment, Adani was told to submit a groundwater management and monitoring plan at least three months before commencement of the project.
The final approval in July, however, changed this to three months “prior to commencing excavation of the first box cut” – which is the point where the ground is opened up to begin mining coal.
This means the full impact upon groundwater will remain a mystery until Adani is poised to commence mining. The Independent Expert Scientific Committee advised the government in May that Adani’s initial attempt at measuring the impact upon water required further work.
The final Department of the Environment assessment, which has to judge whether proponents are of suitable character, also states: “Adani Group has a history of responsible environmental and community management applied to similar projects in other countries.”
This is despite an arm of the company being fined for numerous environmental breaches in India, as well as being accused of violations of workers’ rights.
Adani submitted suggested amendments to 14 of the draft conditions, largely to bring them in line with an approval already granted by the Queensland government. The company sent the proposed changes on 3 July, with the amended final decision made on 14 July.
Adam Walters, spokesman for Greenpeace, said the final approval pays “lip service” to environmental protection.
“It makes it completely legal for no one to understand the impacts of the project before it starts and for it to be shoved into a backroom process with no public scrutiny,” he told Guardian Australia. “The monitoring of water has been found to be inadequate by an independent body but rather than force Adani to assess it properly, the government has given it the green light.
“Groundwater is the lifeblood of that region. There are special springs near the mine, real oases of life in a very arid area. We won’t know what the impact on them will be.
“We also have an approval based on the word of Adani that they know where to get offset habitat, so they are able to destroy valuable habitat without securing a replacement. There are species that will suffer a very uncertain future because of this.
“This shows the system is broken, that the government is weak on these issues and didn’t stand up to the miner on this.”
Government documents highlighting the potential “pros and cons” of the project show that it will contribute $2.97bn each year to the Queensland economy at full export capacity, creating 3,920 jobs once it is operational.
However, it states the mine will also cause living costs to rise, “labour market drain from other sectors into the mining industry”, increased pressure on community services and “reduced amenity for landholders.”
The Carmichael mine will transport coal to an expanded port at Abbot Point by a 388km rail line. On Monday, the Queensland government announced it will take a “short-term financial stake” in the rail line as part of a strategy to fund Galilee basin coal projects to ensure they eventuate.
A raft of international banks, including Citi, Deutsche Bank, Royal Bank of Scotland, HSBC and Barclays, have explicitly ruled out funding Adani’s project. The mine development has raised environmental concerns, due to its impact on climate change and the Great Barrier Reef, as well as financial uncertainty due to the depressed price of coal.
A spokesman for the Department of the Environment said the change to the groundwater requirements was taken “to better align the timing for the plan with the expected project stage when impacts to groundwater will potentially start to occur”.
“The magnitude of the likely impacts on groundwater were taken into account when the project was approved. The project will be staged over a number of years, and any impacts on groundwater are expected to occur after work commences on the bulk earthworks (box cut) required for underground or open-cut mining.”
The spokesman added that Adani will be expected to “actively manage” the mining site for endangered species while replacement habitat is found.
A spokesman for Adani said: “The approval of the Carmichael mine was the subject of some of the most strict and stringent conditions ever imposed on a project in this country.
“We welcomed the approval then, and will adhere to its conditions. The approvals process in place is as stringent, if not more so, than those that apply in comparable jurisdictions.”